Summary
The developer lined up for the Cuyler Best waterline looping project filed for bankruptcy, so the city retracted the unexecuted cost-sharing agreement. The project itself is still expected this calendar year.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Apr 13, 2026.
Impact analysis
No change — the agreement was never fully executed.
Residents who will still get the improved waterline on schedule.
Mentions & discussions (2)
City Council - Apr 13, 2026
The developer lined up for the Cuyler Best waterline looping project filed for bankruptcy, so the city retracted the unexecuted cost-sharing agreement. The project itself is still expected this calendar year.
City Council - Mar 16, 2026
The city is finally connecting two dead-end water lines to fix low water pressure in the Mimosa Drive area. Doing the work in-house saves over $300,000 versus hiring a contractor, and the developer pays 60% back. Residents should know pressure won't fully improve until a separate Wayne Memorial Drive repair is done.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Goldsboro
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.